Managing Shipyard Repair Contracts

Specification, bid and contract define the shipyard work. During execution, variations, tests and outstanding work must remain linked to authorised decisions and the agreed redelivery.

repair contractshipyardBIMCO RepairCon

Operational Explanation

The contract allocates scope, price, time, responsibility, insurance, variations, tests, delivery, warranty and disputes. Preparation must start early enough for the actual project; intervals such as 6, 9 or 12 months are planning examples, not mandatory standards.

BIMCO REPAIRCON 2018 is a standard ship-repair form that can be adapted. The form, rider clauses, law and jurisdiction should be reviewed together by technical, procurement and competent advisory functions.

The working process connects each decision to evidence: the specification describes the work, the bid prices it, variations record what changes and tests show the result. This makes it possible to reconstruct what was planned and what was actually performed.

Regulatory Reference

BIMCO REPAIRCON 2018 is a contractual reference for repairs, adaptable to conversions. Signed terms, amendments, applicable law and statutory/class requirements must be examined within their respective scope; the form does not set a universal docking timeline.

In the REPAIRCON 2018 sample, clause 5(c) connects redelivery with necessary inspections and tests; the signed protocol identifies agreed work to be completed afterwards. Operational records should assign each outstanding task an owner, deadline and acceptance check. Always check amendments and riders in the signed contract. REPAIRCON 2018 sample, clause 5(c).

In the sample, 5(c)(iii) requires the yard to rectify defects at its cost before redelivery unless the owners agree that certain work may be completed afterwards. A punch list alone does not authorize deferral: document the agreement and identify outstanding work in the redelivery and acceptance protocol under 5(c)(iv).

The sample links additional work and reductions to records of changes in price and contract period. For the actual project, check the process and authority provided in the signed contract. REPAIRCON 2018, 1 and 2(a)(iii)–(iv). BIMCO: current REPAIRCON 2018 edition.

Scope of Application

Repairs and conversions placed with a yard. Internal responsibility and approval authority follow Company organization and contract; they do not universally belong to one role.

Procedure / How to Complete It

  1. Define scope, standards, drawings, inclusions, exclusions and acceptance criteria.
  2. Check yard capability, availability, subcontractors and interfaces.
  3. Compare bids on a common basis and clarify extra-work rates.
  4. Negotiate variations, delay, liability, insurance, payment, warranty and disputes.
  5. Define authority, records, hold points, tests and close-out.

During the work, link each discovery to the specification item: description and measured quantities, reason for the change, decision by authorised persons, cost and schedule impact. Track unresolved matters. Technical agreement that work is needed and commercial approval of the extra may require separate evidence under the contract.

Practical Example

For steel renewal, the specification defines areas, grade, tolerances, NDT, class attendance and acceptance criteria; the bid separates base scope from unit rates for added quantities found after opening.

If the area requiring renewal increases after opening, link the finding to its location and measurements, the relevant price item and the decision on the variation. At close-out, link executed quantities to inspection reports; record any outstanding work in the redelivery agreement with its subsequent verification.

What Typically Goes Wrong

Ambiguous scope or uncoordinated clauses turn each discovery into a dispute over price, time and responsibility. A fixed start date does not compensate for incomplete specifications.

Common Mistakes Mistake Library

MistakeConsequenceHow to avoid it
Extra work performed without a traceable decisionPrice, quantities and schedule impact may become disputed.Link the finding, variation and approval to the contract’s authority and process; retain the evidence.
Timeline presented as a standardFalse assurancePlan from the actual critical path
Form used without adaptationRisks not allocatedCoordinate form, riders and applicable law

What the PSCO Checks

PSC does not interpret the private repair contract; it checks ship compliance and applicable documents. Contract acceptance does not prove regulatory compliance.

Operational Tips

Preparation checklist

FAQ

Does REPAIRCON prescribe when planning must start?
No. Timing follows the project and ship due dates.
Which BIMCO edition is cited?
REPAIRCON 2018.
Is the standard form sufficient without riders?
Not necessarily; it must be adapted to scope, risk and applicable law.
Is completed work automatically accepted?
Compare execution with agreed criteria and tests and the contract’s acceptance process. Redelivery, outstanding work and ship compliance require their respective evidence.