Heavy Lift Cargo and Project Cargo
Heavy lift and project cargo require reliable data and an engineering package consistent with the CSM and ship limits; Annex 13 authorises neither autonomous crew calculations nor a universal independent sea-fastening survey.
Operational Explanation
Annex 13 provides design assumptions and an assessment method for semi-standardised and non-standardised cargo. The arrangement must nevertheless be covered by the approved CSM or engineering/case-specific analysis prepared by competent personnel and accepted or approved as required. Deck/tank-top limits, stability, grillage, support and sea fastening remain part of the engineering package.
Regulatory Reference
SOLAS VI/5.6, approved CSM and CSS Code Annex 13 as revised by MSC.1/Circ.1623. Weather-dependent lashing, routing or speed restrictions are used only when formally provided in the CSM/engineering package with applicable limits and monitoring.
Scope of Application
Heavy lift, out-of-gauge and project cargo require assessment proportionate to mass, geometry, supports, CoG, structure and voyage. Approval/acceptance and independent survey depend on Administration, class, CSM, Company, contract, charterer or insurer; they are not identical universal IMO duties for every cargo.
Procedure / How to Complete It
- Obtain reliable mass, dimensions, verified CoG, support and lifting points from the shipper.
- Check deck/tank-top limits, stability, structural loads and compatibility with the approved CSM.
- Have competent personnel prepare securing/sea-fastening analysis under Annex 13 and other applicable standards.
- Obtain acceptance/approval and survey where required by documents and competent parties.
- On board verify installation against drawings and calculations; stop on discrepancy.
Practical Example
For a turbine on deck, the engineering package checks supports, grillage, deck loads, stability, design accelerations and sea fastening. Weather or speed limits apply only if formally included. Crew verify installation against accepted drawings.
What Typically Goes Wrong
Common Mistakes Mistake Library
| Mistake | Consequence | How to Avoid It |
|---|---|---|
| Improvised onboard Annex 13 calculation | Structural assessment and acceptance process are missing | Use competent engineering and approved/accepted package |
| Forecast freely reduces design loads | Arrangement falls outside approved assumptions | Use weather-dependent limits only where formally prescribed |
| Independent survey treated as universal IMO duty | Requirement unsupported by the source | Check contract, insurer, Company, class and Administration |
What the PSCO Checks
Operational Tips
- Do not use estimated data where mass or CoG requires verification.
- Do not reduce design loads from forecast alone.
- Check the sea-fastening survey requirement in contract and applicable procedures.
Preparation checklist
- Reliable cargo data and verified CoG
- Deck/tank-top, stability and structural loads checked
- Engineering analysis prepared by competent personnel
- Acceptance/approval obtained where required
- Weather-dependent limitations formally documented
- Independent survey performed only where required
- Installation matches drawings
FAQ