Loading/Discharging Plan

The SOLAS VI/7 and BLU Code ship/shore plan concerns bulk carriers handling solid bulk cargo; other operations follow their specific regime, approved manuals, SMS and applicable procedures.

cargo operationsloading planstabilitySOLAS

Operational Explanation

For a bulk carrier and solid-bulk terminal, SOLAS VI/7 requires a loading or unloading plan agreed by the Master and terminal representative, with applicable sequences and limits; the BLU Code provides operational guidance. Containers, liquid bulk and other cargoes follow different regimes, manuals and procedures.

Regulatory Reference

SOLAS VI/7: loading, unloading and stowage of bulk cargoes. BLU Code A.862(20): ship/terminal guidance linked to VI/7. IMSBC Code: classification and carriage of solid bulk cargoes. For packed containers, SOLAS VI/2 requires VGM in time for the final ship stowage plan and prohibits loading without VGM.

Scope of Application

SOLAS VI/7 ship/shore plan: a bulk carrier loading or unloading solid bulk cargo at a terminal. For other ships and cargoes use the operating plan required by the specific regime, approved manuals, SMS and Company/terminal procedures. Use the loading computer where fitted and required for the ship and operation.

Procedure / How to Complete It

  1. Identify ship, cargo and applicable regime.
  2. For solid bulk/bulk carrier agree sequence, quantities, rates, ballast and ship/shore limits under SOLAS VI/7 and BLU.
  3. Use the loading computer or approved tools where prescribed for the ship and manual.
  4. For containers obtain VGM before the final stowage plan and in any event before loading; preliminary planning may precede it.
  5. Stop the operation if it becomes unsafe or exceeds agreed limits.

Practical Example

A bulk carrier agrees sequences and rates with the terminal in the SOLAS VI/7 plan. A container ship instead prepares a preliminary plan and finalises it when VGMs arrive: a container without VGM is not loaded.

What Typically Goes Wrong

Applying the BLU model to every ship type or turning the loading computer into a universal requirement. The opposite error is treating VGM as necessary for any planning, instead of for the final stowage plan and loading.

Common Mistakes Mistake Library

MistakeConsequenceHow to Avoid It
Ship/shore plan applied outside its scopeWrong operating regimeIdentify ship, cargo and applicable basis
Intermediate stages not checked with prescribed toolsStructural or stability limits exceededUse loading computer or other approved tools where required
Actual sequence departs from agreed planConditions remain unevaluatedStop, reassess and formally record the change

What the PSCO Checks

Control follows the regime applicable to ship and cargo: ship/shore plan under SOLAS VI/7, approved manuals and limits, VGM for packed containers and consistency between plan and actual operation.

Operational Tips

Preparation checklist

FAQ

Is the BLU plan mandatory for every ship and cargo?
No. The agreed SOLAS VI/7 plan concerns loading/unloading solid bulk cargo on bulk carriers; other operations follow their own regime.
Can no plan exist without VGM?
Preliminary planning may exist; VGM must arrive in time for the final ship stowage plan and the container cannot be loaded without it.
Must the loading computer always be used?
Where prescribed by the ship's equipment, manuals and requirements applicable to the operation.