Boiler Water Treatment
Parameters, sampling points, limits, frequencies, chemistry, conductivity/TDS and blowdown must follow the maker/supplier-specific programme incorporated in PMS/SMS; there are no universal six daily tests or 1,000 µS/cm limit.
Operational Explanation
Parameters, sampling points, limits, frequencies, chemistry, conductivity/TDS and blowdown must follow the maker/supplier-specific programme incorporated in PMS/SMS; there are no universal six daily tests or 1,000 µS/cm limit.
Regulatory Reference
ISM Code 10, boiler maker manual, approved water-treatment supplier programme and PMS/SMS.
Scope of Application
Specific boiler design/pressure, feed/condensate system, chemical programme, sample point, temperature correction and test method.
Procedure / How to Complete It
- Use only installed-programme parameters, points and frequencies.
- Sample and temperature-correct by prescribed method.
- Compare trends and ship-specific limits before dosing/blowdown.
- Investigate abnormal trends before changing chemistry or blowdown.
- Do not add phosphate, alkalinity builder, scavenger or polymer outside the programme.
Practical Example
A conductivity rise is verified with correct sample point/method; the team investigates contamination before using blowdown minutes or dosing from another boiler.
What Typically Goes Wrong
Imposing six daily tests, declaring polyelectrolyte superior, using 1,000 µS/cm, 15 minutes/watch or universal numerical dosing.
Common Mistakes Mistake Library
| Mistake | Consequence | How to Avoid It |
|---|---|---|
| Imposing six daily tests, declaring polyelectrolyte superior, using 1,000 µS/cm, 15 minutes/watch or universal numerical dosing. | Non-compliant decision or treatment | Follow the approved arrangement and applicable sources |
What the PSCO Checks
Operational Tips
- Separate current requirement, class/maker, SMS and voluntary guidance.
- Do not improvise tests, thresholds or intervals.
- Record deviations and corrective action.
Preparation checklist
- Approved programme
- Correct parameters/points
- Ship-specific limits
- Trend investigated
- Dosing/blowdown authorised
FAQ
Related Topics