Operational guide · Operational procedure

Critical Spare Parts Management

Once critical equipment has been identified, the question becomes: if it fails today, is the spare part really on board? Critical spare parts management answers exactly that.

critical sparescritical spare partsOCIMFlogistics

Operational Explanation

Once critical equipment has been identified under the ISM Code, managing the related spare parts becomes itself a safety element: a sudden failure on a critical component with no spare available on board can turn routine maintenance into a prolonged emergency, especially far from ports with spare parts availability.

ISM 10.3 sets no universal spare quantities. The Company defines reliability and availability measures consistent with risk, redundancy, applicable requirements and the SMS. OCIMF guidance is an industry reference: it does not exclude specific flag, class or approved-arrangement requirements. Commitments incorporated into the SMS must be implemented even where they originate in voluntary guidance.

Management aims to keep an identified, compatible and usable spare available, following it from selection through replenishment after use. An inventory entry must be compared with actual availability and the ability to use the part on board.

Regulatory Reference

ISM Code 10.3–10.4: the Company identifies equipment and systems whose sudden failure may create hazardous situations; the SMS provides specific reliability measures, including regular testing of standby arrangements and equipment not in continuous use, integrated into the maintenance routine. Paragraph 10.3 does not set minimum spare quantities. ISM Code, section 10.

The OCIMF Safety Critical Equipment and Spare Parts Guidance, second edition 2026 proposes a risk-based approach to identifying and managing spares. It is industry guidance, distinct from requirements applicable to the ship and procedures adopted by the Company in the SMS.

Scope of Application

Spares that risk assessment, maker information, operating experience, redundancy and the SMS/PMS process identify as necessary to manage failure of critical equipment. ISM 10.3 does not require every spare for every critical item to be carried on board.

Procedure / How to Complete It

  1. Link equipment, failure and spare. Start with the critical equipment list and the effects of the failures considered; assess which components are needed for maintenance or recovery, using maker information, redundancy and operating experience.
  2. Define the strategy. Document intended quantities, location and justification under the SMS and applicable requirements. Consider route, resupply times and the actual ability to use the part. A decision not to carry a component must be justified in the risk assessment.
  3. Identify and check the stock. Record the component code and compatible equipment, actual quantity and location. Check storage condition and shelf life at the defined intervals; also verify the availability of the means, materials and competence needed to use it under the relevant instructions.
  4. Follow consumption and replenishment. Record withdrawal and update stock; initiate reorder under Company thresholds, responsibilities and approvals. If availability falls below the intended level, report the shortage and have the risk and measures for the waiting period assessed. An order placed is not an available spare.
  5. Complete the cycle. On delivery, check identity, compatibility and condition before updating availability. Review the strategy when equipment, service, route or procurement times change; also verify arrangements for shore stocks.

Practical Example

For a critical auxiliary pump, the Company documents the intended spares, on board or ashore, storage conditions, shelf life, reorder point and purchase authority. The responsible person checks that the identified component is compatible with the installed pump and actually usable.

A spare is consumed during maintenance. The PMS job retains the outcome of the work; the inventory records withdrawal and reorder. If the remaining stock no longer meets the intended strategy, the shortage stays visible until replenishment and the Company assesses the risk during the waiting period. Inspection frequency follows the ship's factors, not a universal interval.

What Typically Goes Wrong

A spare list not aligned with failure effects, a carried but deteriorated part, an ignored lead time or unverified shore availability can prolong failure of essential equipment.

Common Mistakes Mistake Library

MistakeConsequenceHow to avoid it
Critical spares list not updated after changes to the identified critical equipmentMissing spares for equipment recently classified as criticalSystematically update the spares list whenever the critical equipment list changes
Critical spares deteriorated due to inadequate storage, never checked until the moment of needThe spare is present but unusable at the moment of failureCheck spare condition at the frequency defined by risk, storage and maker
Reorder started only after the stock is completely exhaustedPeriod of vulnerability with no spare available while awaiting reorderDefine reorder thresholds and responsibilities before stock is exhausted

What the PSCO Checks

Where the condition of essential equipment or SMS evidence makes the subject relevant, the PSCO may examine maintenance, failures and the availability of means for recovery. Prepare the spare strategy, actual inventory, shortages and actions in progress. ISM 10.3 contains no universal list of minimum quantities: specific requirements applicable to the ship still have to be met. More detailed operational controls follow the clear grounds and safety conditions in the PSC procedures.

Operational Tips

Preparation checklist

FAQ

Are the OCIMF guidelines on critical spares mandatory?
They are industry guidance, not a mandatory rule assigning universal quantities. The Company defines the strategy and stocks based on risk and applicable requirements. Commitments incorporated into the SMS must be implemented.
What to do if a critical spare cannot be stored on board due to size or cost?
The Company must justify the decision in the risk assessment and plan realistic shore availability, considering delivery times, route and the ability to use the part. A supplier agreement does not remove the risk during the waiting period or replace any specific carriage requirement.
How often should the condition of stored critical spares be checked?
Frequency follows criticality, storage conditions, shelf life and maker instructions, together with applicable requirements and the SMS. Do not assume a universal six-month interval; also verify compatibility, actual quantity and readiness for use.